Connect the Dots Release Timeline

Week 1

Dev: 10h
Design: 10h
PM: 6h

August 30

  • reset timelines

September 2

  • Finish implementation of Connect the Dots tool ready for QA
  • Finish implementation of homepage re-design ready for QA
  • Re-book video equipment for workshop

Week 2

Dev: 0
QA: 10h
Design: ?
PM: 5h
PI: 5h

September 6-7

  • QA on Tool/Homepage
  • QA on language integration
  • Homepage+connect the dots copy Doc finished

September 8-9

  • Product overview and fix prioritizing based on QA (5h max)
  • Homepage+connect the dots copy Doc finished

Week 3

Dev: ~5h
QA: 10h
Design: ?
PM: 15h
Video: 8h

  • Dev does initial bug and feature fixes before workshop
  • Book video equipment/date for lab video shooting
  • Homepage+connect the dots copy integrated site to generate PO file
  • Homepage+connect the dots copy Doc + PO file sent to translators

September 15

  • Workshop to test Connect The Dots
  • filming of interviews and b-roll footage

September 16

  • Activity guide editing and changes made before committing to copy
  • Finalize video script and send to translators
  • footage dump and binning
  • Product overview and fix/feature prioritizing based on workshop feedback (5h max)
  • Homepage+connect the dots copy Doc + PO file sent to translators

Week 4

  • Dev pushes through changes and fixes based on QA/prioritizing (5 hours)
  • Dev pushes translation PO file (if ready)
  • Connect the dots scripted video portion shooting at lab
  • Integrate English Activity Guide content into indesign, export pdf

September 22

  • Last day of Stephen on project
  • Complete Portuguese and Spanish translations of video script
  • Complete Portuguese and Spanish translations of Activity Guide content

Week 5

  • editing of video and review for final changes

Week 6

  • final edits and after effects work on video, uploaded to vimeo.
  • Integrate Portuguese and Spanish translations of captions into vimeo
  • Integrate Portuguese and Spanish translations of Activity Guide content into indesign, upload pdfs to site

Week 7

October 14

  • Release Launch