Summary
Coordinate the theming, component, and desktop infrastructure work required to
take the Fluent UI React Native agentic stack from its current experimental
state through beta and production readiness.
This is the parent tracking issue. The three linked workstreams define their
beta and production outcomes, staging, dependencies, and exit criteria; each
workstream in turn tracks its implementation issues. Suggested additions remain
decision-gated until they are explicitly added to the program.
Workstream tracker
| Workstream |
Research |
Suggested additions |
Beta delivery |
Production delivery |
| Theming |
Complete |
All promoted |
Not started |
Not started |
| Components |
Complete |
2 pending review |
Not started |
Not started |
| Infrastructure |
Complete |
6 pending review |
Not started |
Not started |
Research outcome
Initial research completed on 2026-08-20 with 46 issue-ready task documents.
The bundle-size and dependency-budget additions approved on 2026-08-21 add one
cross-workstream infrastructure task. The next approved expansion adds six
theming tasks, three component tasks, and three infrastructure tasks, bringing
the program total to 59.
| Workstream |
Task documents |
Key result |
| Theming |
12 |
Defines one design-package contract plus generated defaults, appearance, drift and snapshot gates, consolidated high contrast, current docs, Storybook integration, optional OKLCH and contrast utilities, and a specification-backed Apple theme. |
| Components |
39 |
Defines testing and readiness contracts, FocusZone and spec ingestion, primitive scope, Button/ToggleButton alignment, shared accessibility conformance, and one task for each of 32 missing catalog components. |
| Infrastructure |
8 |
Covers driver landing and release proof, Storybook E2E and Win32, bundle budgets, smoke-harness disposition, Windows visual evidence, and portable real-platform accessibility assertions. |
The original requested scope is fully represented. The extra desktop-driver
release task is an evidence-backed split of implementation landing from
real-platform proof. Owner-approved Suggested Additions are promoted into the
task hierarchy; the two remaining component additions and six remaining
infrastructure additions stay decision-gated.
Current delivery gaps
- The desktop driver's macOS backend still needs clean-machine proof, and all
three desktop endpoints need required CI gates before production.
- The provisional component assessment places all 23 current exports at
experimental because no item has pinned spec provenance and two-platform
on-device validation yet; the component task records the higher ceiling each
item could reach after those universal gaps close.
- No repeatable bundle-size or dependency-budget gate currently makes the
component package boundary and theming optionality claims enforceable.
Program staging
Stage 0: Approve scope
Stage 1: Establish beta foundations
Stage 2: Deliver beta
Stage 3: Harden for production
Cross-workstream dependency order
- Approve the theming public contracts, component readiness model, spec
ingestion boundary, and infrastructure architecture.
- Land reusable theming and testing foundations before scaling component
generation.
- Generate and assess missing components in dependency-aware waves.
- Exercise beta candidates through Storybook and the desktop test pipeline.
- Harden compatibility, performance, accessibility, release automation, and
operational ownership for production.
The detailed workstream plans may refine this order when repository evidence
requires a stricter dependency.
Completion rules
Research is complete when every owner-listed task has an evidence-backed task
document, internal links resolve, beta and production scope are explicit, and
Suggested Additions remain clearly separated for owner review. Delivery
checkboxes should only be updated from merged code, passing required
validation, or another cited durable result.
Summary
Coordinate the theming, component, and desktop infrastructure work required to
take the Fluent UI React Native agentic stack from its current experimental
state through beta and production readiness.
This is the parent tracking issue. The three linked workstreams define their
beta and production outcomes, staging, dependencies, and exit criteria; each
workstream in turn tracks its implementation issues. Suggested additions remain
decision-gated until they are explicitly added to the program.
Workstream tracker
Research outcome
Initial research completed on 2026-08-20 with 46 issue-ready task documents.
The bundle-size and dependency-budget additions approved on 2026-08-21 add one
cross-workstream infrastructure task. The next approved expansion adds six
theming tasks, three component tasks, and three infrastructure tasks, bringing
the program total to 59.
The original requested scope is fully represented. The extra desktop-driver
release task is an evidence-backed split of implementation landing from
real-platform proof. Owner-approved Suggested Additions are promoted into the
task hierarchy; the two remaining component additions and six remaining
infrastructure additions stay decision-gated.
Current delivery gaps
three desktop endpoints need required CI gates before production.
experimentalbecause no item has pinned spec provenance and two-platformon-device validation yet; the component task records the higher ceiling each
item could reach after those universal gaps close.
component package boundary and theming optionality claims enforceable.
Program staging
Stage 0: Approve scope
workstreams.
links in the corresponding workstream.
Stage 1: Establish beta foundations
ingestion.
Storybook endpoints needed by beta validation.
Stage 2: Deliver beta
production gaps.
Stage 3: Harden for production
and release gates defined by the workstreams.
maintenance.
Cross-workstream dependency order
ingestion boundary, and infrastructure architecture.
generation.
operational ownership for production.
The detailed workstream plans may refine this order when repository evidence
requires a stricter dependency.
Completion rules
Research is complete when every owner-listed task has an evidence-backed task
document, internal links resolve, beta and production scope are explicit, and
Suggested Additions remain clearly separated for owner review. Delivery
checkboxes should only be updated from merged code, passing required
validation, or another cited durable result.
by one cross-workstream infrastructure task.
Infrastructure additions 1, 2, and 8 have issue-ready task documents.